Gross Incompetence / Case File 01

Left to Dry How a Known Danger in Iowa Became an Emergency

On November 25, 2026, the Army blew up five tons of degraded lead azide outside Middletown, Iowa. The blast went well. Everything that made it necessary did not: a warning on record for seven months, a stabilizer nobody topped up, a safer fix dropped without explanation, and a system that rewards neglect with a shortcut.

November 25, 2026 · Emily Adams · About 17 Minutes

9,700Pounds of degraded lead azide in 68 barrels
7 mo.From the August 2025 warning to the Army telling the EPA
4 daysFrom the safer treatment plan to the decision to blow it up
1977The last lead azide detonation this size, per the Army

At 9 a.m. on November 25, 2026, the United States Army blew up five tons of explosives in southeast Iowa on purpose, because nobody had taken care of them.

That’s the whole story in one sentence. Everything else is detail, and the detail is worse. The material was lead azide, 68 barrels of it, about 9,700 pounds, sitting in earth-covered bunkers at the Iowa Army Ammunition Plant outside Middletown. AP reported it was the nation’s entire stockpile. It had dried out, crystallized and turned so touchy that the Army decided nobody could safely move it, open it or neutralize it. So the only option left was to set it off where it sat and try to keep the lead dust from landing on the neighbors.123

The Army is calling the blast a success, and on the narrow question of the blast, early readings back that up. That’s not the question this piece is about. The question is how a known danger sat in a bunker long enough to become an emergency, and why the slower, safer fix got dropped on the way. The answer isn’t one bad actor. It’s a system that worked exactly as designed. So let’s walk through it.

What Blew Up This Morning

Here’s what happened, as the officials involved describe it.

Two rapid detonations went off around 9 a.m. local time. Before that, crews had built two-story walls of concrete and sand around the bunkers, staged ballistic gels and foams meant to trap lead dust, and set up a wall of water the Army put at more than 100,000 gallons. Maj. Gen. Eric Shirley of Army Sustainment Command said fire trucks delivered more than 3,600 gallons of foam and that there were no secondary explosions and no damage to buildings. He said every barrel was “definitively removed.”435

The EPA said its real-time monitors showed zero airborne lead across the region in the first hours after the blast. Gov. Kim Reynolds called it “a best-case scenario” and later a “flawless detonation.” EPA Administrator Lee Zeldin was more careful: he said he would not declare everything safe until the sampling data was released, and he told residents to stay inside with the windows shut.45

The people who live there did not have a normal Wednesday. FEMA moved residents out of a five-mile zone running southwest of the plant and put them in hotels through Friday. Pregnant women, children under six and people with chronic illness were told to leave the modeled plume area. Schools canceled classes. Reynolds declared a disaster emergency for Des Moines, Lee and Van Buren counties. Illinois partly activated its emergency center. Missouri watched for the plume. The U.S. Department of Agriculture said about 350 farms could be affected.436

Col. Aaron Teller, who commands the Army’s 71st Explosive Ordnance Disposal Group, said the last lead azide detonation of this size was in 1977.4

So it went about as well as a planned explosion of five tons of lead can go. Keep that in mind, because the rest of this is about everything that happened before 9 a.m.

What Lead Azide Is, and Why “Degraded” Matters

Lead azide is a primary explosive. Its job is to go off easily, so it can set off the bigger, more stable charge in a detonator or a round of ammunition. It’s sensitive to friction and shock on purpose.7

Because it’s that touchy, it’s stored wet. The Army kept this material under a mix of water and ethanol, which keeps the crystals from rubbing, sparking or drying into something worse. As long as the liquid is there and checked, the material is manageable.8

When the liquid goes, the problem changes. The material can recrystallize into forms that are far more sensitive. The Army says that’s what happened here: inspectors found partly crystallized lead azide, including crystals on the outside of the barrels and in the lids. That’s why it couldn’t be moved. Opening a lid could set it off. A jolt from a forklift could set it off. A hard freeze could make it worse.9810

And then there’s the lead. It’s in the name. Blow up lead azide and you get lead dust, and Iowa’s own health department says no safe level of lead exposure has been identified. If you’ve read the Lead Poisoning deep dive on this site, you already know what lead dust does to small children. If you haven’t, the short version is that it doesn’t come back out.1112

Here’s the rule to keep in your pocket for the rest of this: an emergency you saw coming isn’t an emergency. It’s a deadline you missed.

How It Ended Up in Iowa

The Iowa Army Ammunition Plant has been loading and assembling munitions since World War II. It’s government-owned and contractor-operated, which means the Army owns the land, the buildings and the explosives, and a private company runs the place day to day. That company is American Ordnance LLC, a subsidiary of the Philadelphia contractor Day & Zimmermann, and it has run the plant since 1998.131415

According to Robert Cekada, the director of the ATF, this lead azide was brought to Iowa from bases around the country in 2009 and stored in barrels in case the military needed it. Al Jazeera reported the material had sat in storage for about twenty years.316

And this wasn’t the first time anyone noticed lead azide going bad at this plant. In 2014, Picatinny Arsenal’s public affairs office published an article about a project to develop “green” replacements for lead azide in detonators. It said that project began in 2004 in response to Defense Department concerns over “a 40-year-old stockpile of lead azide deteriorating” at the Iowa Army Ammunition Plant. The article doesn’t say what happened to that stockpile, and nobody has said publicly whether it’s the same material that blew up this morning. But it means the Army has known for more than twenty years that lead azide was rotting in Iowa.17

So by the time anyone in Middletown heard the words “lead azide,” the stockpile had already been on the books for a long time, under multiple administrations of both parties. Hold onto that. It’s going to matter when the finger-pointing starts.

Seven Months of Silence

This is the part of the record that should bother everyone, and it comes mostly from the government’s own filings and from reporting by Iowa Public Radio.

  1. August 2025

    The plant’s operator, American Ordnance, warns a disposal company called MuniRem that the same 68 drums are “potentially unstable.” That’s according to MuniRem’s CEO, Valentine Nzengung. No document from American Ordnance has been published to confirm it.8

  2. September 2025

    The water and ethanol mix that keeps the lead azide stable stops being checked or topped up. That isn’t an activist’s claim. It’s in the government’s own court brief, backed by a sworn declaration from Col. Teller, which says the drums couldn’t be safely opened to refill it, and that as the mix evaporated it became more likely to freeze.8

  3. September 24, 2025

    American Ordnance asks MuniRem for a quote to dispose of the material, according to documents MuniRem shared with Iowa Public Radio.8

  4. March 12, 2026

    The Army notifies the EPA that it has a problem. That’s about seven months after the August warning.818

Read those four lines again. A warning is on record in August. The thing that keeps the explosive stable stops being maintained in September. A disposal quote is requested in September. The regulator hears about it in March.

Now here’s the cause and effect. The Army’s main reason for blowing this up instead of treating it is that the material became too sensitive to move or open. The material became that sensitive, at least in part, because its stabilizing liquid went unmaintained for months. So the neglect created the condition, and the condition justified the shortcut.

There’s a wrinkle, and it should be stated plainly. Col. Teller said on November 24 that the barrels “deteriorated rapidly over the past eight months,” which points to roughly March 2026, not August 2025. That doesn’t square with a warning in August that the drums were already unstable. Either the August warning overstated things, or the deterioration started well before the Army says it did. Nobody has reconciled the two, and that’s one of the first things an investigation should settle.8

The Safer Option That Got Dropped

There was another way to do this, and for a while, the Army was doing it.

  1. March 19, 2026

    A panel of Army specialists, researchers from the Johns Hopkins Applied Physics Laboratory and EPA representatives votes to recommend chemical neutralization as the safest method. This comes from MuniRem’s chronology. Army lab tests at Picatinny Arsenal reportedly neutralized the material in 15 to 20 minutes.8

  2. March 25, 2026

    The Army hires MuniRem. In April, contract documents name MuniRem’s chemical as the preferred option.818

  3. April 2, 2026

    The EPA issues the first of three emergency storage permits.8

  4. May 4, 2026

    Around this date, MuniRem submits its detailed treatment plan, describing how its chemical could reach residue at the lids and seals so crews could open the drums and treat what was inside.8

  5. May 8, 2026

    Then-Army Secretary Dan Driscoll selects “in-place, controlled, intentional detonation.” The same day, the contracting officer tells MuniRem that reviewers need more time and asks for a technical meeting. According to Nzengung, that meeting never happens.8

  6. May 14, 2026

    The Army tells MuniRem it won’t exercise the treatment part of the contract. The contracting officer calls detonation the safest method, chosen out of an “abundance of caution.”8

So the decision was made four days after the plan arrived, on the same day the Army asked for more time to review it.

What’s revealing is the email the New York Times later reviewed, from an Army contracting officer, which said the cancellation was unrelated to any shortcomings in MuniRem’s technical proposal. Read that the way a normal person would. The plan wasn’t the problem. Then what was?18

The Army’s answer, given in a letter to the EPA in September, is safety. It says its working group “unanimously” ruled out chemical treatment because crystals may have migrated into the lids, opening a drum could cause an explosion, mixing in a chemical could disturb the explosive, and moving the drums could set them off. The EPA’s regional administrator, Jim Macy, backed that up, citing Army data showing the material had recrystallized. Teller said on November 24 that officials “were never able to find a viable alternative.”818

That may well be true by November. But notice two things.

First, the “unanimous” working group and the March panel that recommended neutralization are described as if they were different bodies, and nobody has said whether they were, or what new information changed the answer between March and May. The joint statement from the EPA, the Army and the Department of Health and Human Services said the operation had been “meticulously” planned since March. It did not address why the contract was canceled.18

Second, the Army acknowledged that chemical treatment would have avoided a lead dust plume entirely. Detonation was always the option that put lead into the air over people’s homes. It was chosen in May. The public got about five days’ notice in November.181

The Machine That Built This Emergency

It would be satisfying to find one villain here. There isn’t one. There’s a machine, and every part of it did what it was built to do.

Part one: a private operator and a public owner

The plant is run by a private company, American Ordnance, under an Army contract. The company does monthly visual inspections of the storage areas. The Army owns the explosives, controls the money for getting rid of them and makes the final calls.1916

That arrangement has a built-in blind spot. When something goes wrong, the contractor can say the Army never funded the fix, and the Army can say the contractor never flagged it in time. Right now we can’t tell which version is true, because nobody has published the contract terms, the inspection logs or the date the Army was first told. Whose job was it to keep that liquid topped up? That single question decides whether this was a company’s failure or the Army’s, and the public doesn’t have the answer.

That’s the point of this part of the machine. Responsibility gets split down the middle until there’s none left on either side.

Part two: the military grades its own homework

The Army has plenty of storage rules. The Department of Defense sets its own explosives safety standards and has its own board to oversee them, the Department of Defense Explosives Safety Board. The Army has its own versions of those rules on top. They cover how far bunkers sit from homes and roads, how much can be stored in one place, and how often things get inspected.2021

What it doesn’t have is much outside oversight of that storage. Under the EPA’s 1997 Military Munitions Rule, waste military munitions stored according to the Defense Department’s own standards can be conditionally exempt from the EPA’s normal hazardous waste storage rules.22

The conditions sound strict on paper. The munitions have to fall under the Defense Department’s explosives safety board and be stored to its standards. Each storage unit has to be reported to the regulator. There’s an inventory once a year and an inspection at least every quarter. Break a condition and the exemption is lost, at least until the military applies to get it back. But look at who sets the standard being followed: the Defense Department.23

Iowa has never taken over its own hazardous waste program, so the EPA’s regional office in Kansas runs it directly. That means the federal exemption has applied at this plant since 1997.24

Put plainly: the people who made the mess write the standard for avoiding it, inspect themselves against it and decide when they’ve passed.

Part three: no deadline to get rid of anything

Here’s the gap that matters most. The storage rules are built to stop an accidental blast tomorrow. They say a lot about distances, quantities and inspections. They don’t force anyone to dispose of aging, unneeded explosives before they rot.

The Army does inspect stored ammunition. Specialists in its ammunition surveillance program check stocks on a cycle and assign them condition codes. But when something is marked unserviceable or no longer needed, it doesn’t go to the front of a line with a due date. It goes into a pile of stuff waiting to be demilitarized, which is the military’s word for taken apart or destroyed. None of the storage rules we found sets a deadline for clearing that pile.25

And the pile is big. The last time the Government Accountability Office counted, in 2015, the Defense Department had about 529,000 tons of ammunition waiting to be destroyed, and expected to add another 583,000 tons over the next five years. GAO put the cost of storing it at about $42 a ton per year, and the cost of destroying it at about $2,000 a ton.26

Do the math the way a budget office does. Storing a ton for a year costs $42. Getting rid of it costs about fifty years’ worth of storage, all at once. If you’re the person deciding where this year’s money goes, letting it sit always looks cheaper, right up until the year it isn’t.

Without a hard deadline, old stockpiles sit until they become someone else’s emergency. That’s what happened here. A stockpile consolidated in 2009 was still in a bunker in 2026.

Part four: the emergency escape hatch

And once it’s an emergency, the rules loosen.

Federal hazardous waste rules let the military treat explosives without a normal permit during an immediate response to “an immediate threat to human health, public safety, property, or the environment,” as long as an explosives or munitions emergency response specialist makes that call. Separately, the EPA can issue a temporary emergency permit, good for up to 90 days, when it finds an imminent and substantial danger. In court, the Justice Department argued the Army didn’t need the EPA’s permit at all because of that exception. The EPA issued an emergency permit anyway on November 13, authorizing the blast outside the plant’s existing hazardous waste permit.18827

That’s the trap. The longer something is neglected, the more dangerous it gets. The more dangerous it gets, the stronger the case for the emergency exception. The emergency exception is what lets the slow, careful process be skipped. Neglect isn’t punished by this system. It’s rewarded with a shortcut.

A Plant With a Record

None of this happened at a spotless facility.

The Iowa Army Ammunition Plant has been on the EPA’s Superfund National Priorities List since 1990. Tests in 1981 and 1983 found TNT, RDX and DDT in wells downhill from the plant. About 100 people drink from private wells within three miles. The cleanup has been going on for more than 35 years and isn’t done.2829

In January 2025, the Army reported an unplanned explosion at the site. Nobody was reported hurt. Iowa Public Radio reports OSHA has investigated and fined the plant multiple times in the past decade. Former workers and their families describe what one called a “heavy culture of silence” about what went on inside. That’s their account, not a finding, but it fits the pattern of everything else in the record.28

A place with that history was trusted to babysit five tons of degraded primary explosive with minimal outside oversight. You can guess how that went, because you just read it.

What They’re Saying, and What the Record Says

Expect to hear these lines a lot over the next few weeks. Here’s how each one holds up.

The Line“It was a flawless detonation.”

The RecordThe blast itself went well by every early measure, and that’s genuinely good news for the people downwind. But a well-executed emergency doesn’t excuse the neglect that created it. Landing a plane in the Hudson is great flying. It’s not a maintenance plan. And “flawless” is premature until the EPA’s soil, dust and water results are public, which Zeldin himself said.45

The Line“This is Obama’s fault.”

The RecordPresident Trump and Vice President JD Vance both said the problem started in 2009, under the Obama administration, when the stockpile came to Iowa. The ATF director confirms the 2009 move. But the material sat there through four presidencies, and the warning, the unmaintained stabilizer, the canceled treatment contract and the decision to detonate all happened in 2025 and 2026. And the Army’s own 2014 article traces concern about deteriorating lead azide at this plant back to 2004, under President George W. Bush. If the storage started the clock, everyone since let it run.53817

The Line“The court approved it.”

The RecordThe Eighth Circuit ruled on November 23 that the Army and EPA “adequately considered” other methods and let the blast go forward. That’s a ruling on whether the November decision was reasonable given the material’s condition in November. It’s not a ruling on how the material got that way. The lawsuit itself is still open.830

The Line“There was no other option.”

The RecordBy November, that may be true. That’s exactly the problem. The other option existed in March, was recommended by a panel, was tested in an Army lab and was under contract. It was dropped in May without a public explanation. “We had no choice” is a lot less impressive when you’re the one who spent the choices.8

The Line“MuniRem just wants its contract back.”

The RecordFair point, and it should be said out loud. MuniRem lost the work, so its account needs backing up. Some of it is backed up: the government’s own court brief confirms the stabilizer went unmaintained from September 2025, and the Army contracting officer’s email says the cancellation wasn’t about the quality of MuniRem’s plan. The parts that rest only on MuniRem’s word, like the August warning and the panel vote, are marked that way here.818

The Line“The environmental groups were just obstructing.”

The RecordThe Iowa Environmental Council and the Sierra Club sued to stop the blast and lost. Sarah Green, who runs the Iowa Environmental Council, says the lawsuit and public pressure pushed the Army to add safeguards that weren’t in place before the original November 20 date. The date moved three times. Whatever you think of the suit, the blast that happened this morning had more protection around it than the one first scheduled.453

What Still Hasn’t Been Answered

These are the questions a real investigation would have to answer. Iowa Gov.-elect Rob Sand has called for “immediate transparency.” Sen.-elect Josh Turek has called for an investigation into the degradation, the choice of method and what else is stored at the plant. Here’s where to start.528

  • Whose job was it to keep the stabilizing liquid topped up? American Ordnance’s under its contract, or the Army’s?
  • Who knew about the August 2025 warning, and when? Is there a document, or only MuniRem’s account?
  • Why did the Army wait until March 2026 to tell the EPA?
  • What changed between March 19 and May 8? Was the “unanimous” working group the same body as the panel that recommended neutralization?
  • Why did the Army choose detonation on the same day it asked for more time to review the treatment plan?
  • Why did the public get about five days’ notice of a decision made in May?
  • What else is in those bunkers, and what condition is it in?

The documents that would answer most of these exist: the operating contract, the inspection logs, the March panel record and the internal memos behind the May 8 decision. They’re the obvious targets for records requests and for discovery in the lawsuit that’s still open.

What Would Have Prevented It

None of these is radical. Every one of them would have changed this story.

  • A hard disposal deadline. Once an explosive is declared obsolete or starts to degrade, the clock starts, and it isn’t open-ended. Funding for disposal gets treated as a safety requirement, not a line item that can slide.
  • Outside inspection of munitions storage. The EPA or the state, not just the Defense Department grading itself. That means rethinking the storage exemption in the Military Munitions Rule.
  • Contracts that name names. Every government-owned, contractor-operated plant should have one party clearly responsible for stabilizing and monitoring stored energetics, with a written deadline to report problems up the chain.
  • Public notice when a stockpile starts to fail. Not when the blast is scheduled. The people of Middletown should have heard about this in March, when the Army told the EPA, not in November.
  • A record of why the safer option was dropped. When the government passes over a method that keeps lead out of the air in favor of one that puts it there, the reason should be written down and published.

The Army deserves credit for the detonation itself. The soldiers and crews who built the walls, staged the foam and pulled it off did hard, dangerous work well.

But that’s the irony that ties this whole thing together. The government was at its most competent at the one moment that only existed because of years of it being incompetent. A five-ton explosion in a farm town, on the day before Thanksgiving, with families in hotels and farmers waiting on soil tests, got called a best-case scenario. That’s what the system produces when it works exactly as designed: emergencies nobody owns, and a round of applause for the cleanup.

Sources

  1. U.S. Army, Public Safety Advisory: Controlled, Mitigated Detonation of Unstable Lead Azide at Iowa Army Ammunition Plant
  2. Associated Press (via KXNET), US Stockpile of Unstable and Dangerous Lead Azide Scheduled for Detonation in Iowa
  3. KCRG and Associated Press, Army Detonates Lead Azide Stockpile at Iowa Ammunition Plant (November 25, 2026)
  4. KCCI, All 5 Tons of Lead Azide Successfully Destroyed in Iowa Detonation, Army Says (November 25, 2026)
  5. Fox News, Live Updates: Army Disposes of 68 Barrels of Lead Azide at Iowa Army Ammunition Plant (November 25, 2026)
  6. Illinois Environmental Protection Agency, Iowa Army Ammunition Plant Updates
  7. Wikipedia, Lead(II) Azide
  8. Iowa Public Radio, Army Chose to Blast Unstable Lead Azide Days After Contractor Submitted a Chemical Treatment Plan (November 24, 2026)
  9. U.S. Army, Army Announces Controlled Detonation of Degraded Explosive Material at Iowa Army Ammunition Plant
  10. U.S. EPA, On-Scene Coordinator Site Profile: IAAAP Lead Azide
  11. Iowa Department of Health and Human Services, Update: Planned Lead Azide Detonation (November 24, 2026)
  12. American Lung Association, Health Guidance for Residents Near Lead Azide Detonation Zone
  13. U.S. Army, Iowa Army Ammunition Plant (February 14, 2023)
  14. U.S. Army, Iowa Army Ammunition Plant Welcomes New Commander (May 17, 2017)
  15. Day & Zimmermann, Munitions
  16. Al Jazeera, Why Is the US Army Detonating Lead-Rich Explosives in Iowa? (November 21, 2026)
  17. Cassandra Mainiero, Picatinny Arsenal Public Affairs, Picatinny Aims for Green With New Type of Primary Explosive (U.S. Army, March 21, 2014)
  18. Iowa Public Radio, Report Shows the Army Canceled a Chemical Treatment Contract Before Opting to Detonate Toxic Explosives in Iowa (November 21, 2026)
  19. Wikipedia, Iowa Army Ammunition Plant
  20. Office of the Under Secretary of Defense for Acquisition and Sustainment, DESR 6055.09, Defense Explosives Safety Regulation (formerly DoD Manual 6055.09-M), Edition 1, Change 2
  21. Department of the Army, DA Pamphlet 385-64, Ammunition and Explosives Safety Standards (2023)
  22. U.S. EPA, Military Munitions Rule, 62 Federal Register 6622 (February 12, 1997)
  23. 40 CFR 266.205, Standards Applicable to the Storage of Solid Waste Military Munitions
  24. Iowa Department of Natural Resources, Special Waste Authorization (hazardous waste program status)
  25. U.S. Army, Transformation of the Army Ammunition Surveillance Program (December 16, 2021)
  26. U.S. Government Accountability Office, GAO-15-538, Defense Logistics: Improved Data and Information Sharing Could Aid in DOD's Management of Ammunition Categorized for Disposal (July 2015)
  27. 40 CFR 270.1(c)(3) and 270.61, RCRA Permit Exemption for Immediate Responses and Emergency Permits
  28. Iowa Public Radio, People Familiar With the Iowa Ammunition Plant See a Complicated Past (November 23, 2026)
  29. U.S. EPA Region 7, Iowa Army Ammunition Plant National Priorities List Fact Sheet (archived)
  30. CNN, US Army to Detonate Explosives in Iowa on Wednesday After Court Green-Lights Plan (November 23, 2026)